Skip to content
1 min read

Delivering Solar Success Under Tight Timelines at Adolga Solar Farm

Company Acciona
Location 20 km northwest of Gladstone
Timeline TBC
Project Overview Adolga Solar Farm is a large-scale solar energy project that is nearing completion. The project required the supply of critical 275 KV electrical equipment, including disconnectors, breakers, capacitive voltage transformers, surge arresters, and insulators.
Products
  • 275 KV electrical equipment
  • Disconnectors
  • Breakers
  • Capacitive voltage transformers
  • Surge arresters
  • Insulators

 

cabecera-aldoga

 

Project Overview

Adolga Solar Farm is a large-scale solar energy project that is nearing completion. The project required the supply of critical 275 KV electrical equipment, including disconnectors, breakers, capacitive voltage transformers, surge arresters, and insulators.

Leveraging the team's previous success on the similar FFI Aldoga project, the team efficiently delivered this equipment within the tight project timeline.

Insulect also provided on-site support and supervision during the installation phase to ensure a seamless commissioning process. The collaborative approach and our expertise as a local manufacturer were key factors in successfully executing this project within the customer's stringent requirements and deadline.

Project Challenges

  • The requirement for hands-on technical support and expertise to be provided on-site to assist the customer with the installation and commissioning process.

Benefits to client

  • Insulects subject matter expertise and proven track record from previous similar projects meant a seamless and speedy delivery.
  • Insulects commitment to a collaborative approach and local presence enabled responsive support to meet tight deadlines.

Critical Sucess Factors

  • Insulect's status as an approved local manufacturer and supplier reassured the client of the product's quality and suitability.
  • The team's local presence facilitated faster response times and enhanced on-site support during installation.
  • Demonstrated commitment to meeting the client's stringent technical requirements.
  • Attention to detail and thorough understanding of the client's specifications ensured that the delivered equipment fully met their needs.
  • Commitment to the tight project timeline through meticulous planning and coordination enabled overcoming the challenges of an aggressive deadline.

 

More Projects